GGAO Site News
Gimbal and Telescope Assembly (GTA) #1 installed in the SGSLR shelter in late June 2022
September 14, 2022
The Gimbal with Mass Simulator was removed from the GGAO SGSLR facility in June 2022 and shipped back to Cobham. After the Factory Acceptance Test at Cobham in Lansdale, the Gimbal and Telescope Assembly (GTA) #1 was shipped to GGAO and installed in the SGSLR shelter in late June 2022. Preparations for the Site Acceptance Testing (SAT) were begun shortly after installation.
The Space Geodesy Project completed the Factory Acceptance Testing (FAT) of SGSLR's Gimbal and Telescope Assembly Unit #1 (GTA#1)
June 27, 2022
The Space Geodesy Project completed the Factory Acceptance Testing (FAT) of SGSLR's Gimbal and Telescope Assembly Unit #1 (GTA#1) in early June 2022 at the manufacturer's facility (Cobham Advanced Electronic Solutions in Lansdale PA). After passing the FAT Review GTA#1 was then shipped to GGAO on June 21st and installed in the SGSLR facility on June 22nd by the prime SGSLR contractor, KBR, Inc. KBR and Cobham are currently preparing the gimbal and optics to start the Site Acceptance Testing (SAT).
New Jackscrew Successfully Installed on GGAO VGOS Antenna
June 17, 2022
A new jackscrew and gearbox assembly were installed on the 12m VGOS antenna system at NASA Goddard Geophysical Astronomical Observatory (GGAO) in Greenbelt, Maryland during the week of June 6 – 10, 2022. The GGAO site operations and engineering management team from Peraton, antenna repair technicians from Intertronics Solutions, Inc. (ISI) – Calian and heavy equipment operations personnel from United Rigging in Beltsville, Maryland supported the repair activities. Replacement of the jackscrew improves overall structural and motion integrity associated with antenna pointing requirements and promotes continuous VLBI scientific research contributions from the NASA/SGP network.
ISI-Calian engineering technician inspects installation of new jackscrew beneath the GGAO 12m dish supported by a horizontal metal beam and hydraulic gantry system as required by NASA safety guidelines.
Gimbal and Mass Simulator installed at GGAO
September 19, 2019
Gimbal #1 and mass simulator (GMS) were crated and shipped from Cobham in Lansdale PA and delivered to GGAO early in the week of September 16th. The riser, which is needed to mate the pier with the gimbal, was also delivered to GGAO early that week. The riser was lifted by crane through the dome slit into place in the SGSLR shelter early in the morning of the 19th and bolted to the pier.
Later that morning, once the riser installation was complete, the GMS was lifted by crane through the dome slit into place in the SGSLR dome area and attached to the top of the riser.
Power and servo controller cables were connected to the GMS. Later that same day, Cobham employees were able to move the mount under computer control through the servo controller. This was followed by NASA/KBR connecting their computer and moving the mount.
The final levelling of the mount still needs to be done, and offsets for the encoders must be determined before star calibrations can be attempted. The mass simulator has a tertiary mirror (no primary or secondary mirrors) but we expect to be able to see enough stars to do a rough initial star calibration.
This installation will allow NASA/KBR to test the performance of the gimbal and also checkout the GTA test software. Meanwhile in Lansdale, Cobham is working to complete gimbal #2 and test it. Once the first telescope is ready, gimbal #1 will be shipped back to Lansdale and mated with the telescope in preparation for the first Gimbal and Telescope Factory Acceptance Test (FAT).
SGP officially takes ownership of the GGAO SGSLR shelter
August 08, 2019
The GGAO SGSLR shelter official inspection took place the morning of Tuesday July 30th. The official punch list for the inside was generated. Participating in this walk through were the Goddard Project Manager for the construction, Quality Assurance, Safety, the Construction team and SGP personnel (Long, McGarry, Donovan and Nelson). After the inspection, SGP officially took ownership of the shelter which is now Goddard building 228. The exterior walk through will occur after the outside stairs are complete.
Dome Site Acceptance Test (SAT) Successful
May 06, 2019
The dome Site Acceptance Test (SAT) was performed Friday morning May 3rd and it was successful. Here is a team picture of the Baader and SGSLR teams in the dome after the successful SAT.
Dome for the SGSLR shelter at GGAO installed
May 02, 2019
The dome for the new SGSLR shelter building at GGAO was assembled by the Baader Planetarium team in the GGAO parking lot. Once the dome was built, on May 1st a crane arrived to perform the lifting. The dome ring, followed by the dome itself, were lifted and installed on the roof.
Progress on the shelter and arrival of the dome parts
April 22, 2019
The shelter continues to progress. The doors and windows are taking shape and the roof is being worked.
The sea container with the dome parts arrived at the port of Baltimore from Germany on April 15th and was delivered to GGAO the morning of April 18th. There was a great deal of excitement at GGAO when it arrived and a lot of the site construction and SGSLR teams were there to greet it. A large forklift was required to remove it from the truck as it weighs over 5000 lbs. It is currently resting just North of NGSLR, waiting for the Baader team to arrive and assemble the parts and then install the dome on the shelter.
The SGSLR dome for the new system at GGAO passes Factory Acceptance Testing (FAT)
March 6, 2019
The SGSLR dome passed Factory Acceptance Testing (FAT) on March 5th at the Baader Planetarium factory outside of Munich Germany. The Baader development team and the three members of the SGSLR team who were at Baader’s facility for the FAT took time the following day for a group photo with the SGSLR dome. This is the dome that will be delivered to GGAO to sit on top of the shelter.
Standing on the dome flap are McGarry, Donovan and Wetzel. Just to the right of the dome is Thomas Baader.
Watch the SGSLR dome in action below.
© Baader Planetarium, Munich, Germany
The shelter for the new SGSLR at GGAO goes up in an all-day-long activity
March 5, 2019
The shelter goes up in an all-day-long activity. The sun is setting as the roof is finally lowered onto the building by crane. MOBLAS-7 can be seen in the left foreground of the picture.
The SGSLR shelter after installation. The building is together but clearly needs a lot of finishing work including adding the door and windows and the interior build out.
The concrete pad for the shelter for the new SGSLR system has been poured
February, 2019
With the Government Shutdown now over, the pad has been poured. MOBLAS-7 is in the background with the telescope in the left most of the three trailers and the aircraft avoidance radar sits atop the center trailer.
News items
September 14, 2022
Gimbal and Telescope Assembly (GTA) #1 installed in the SGSLR shelter in late June 2022
June 17, 2022
New Jackscrew Successfully Installed on GGAO VGOS Antenna
September 19, 2019
Gimbal and Mass Simulator installed at GGAO
August 08, 2019
SGP officially takes ownership of the GGAO SGSLR shelter
May 06, 2019
Dome Site Acceptance Test (SAT) Successful
May 02, 2019
Installation of the dome
April 22, 2019
Progress on the shelter and arrival of the dome parts
March 6, 2019
The SGSLR dome passes Factory Acceptance Testing (FAT)
March 5, 2019
The shelter goes up in an all-day-long activity
February, 2019
The concrete pad has been poured